e|agenda.NET Sarasota County Schools |
THE SCHOOL BOARD OF SARASOTA COUNTY, FLORIDA Landings Administrative Complex 1980 Landings Blvd. 3:00 P. M. |
Agenda Item #38 Title ACCEPTANCE OF SUBSTANTIAL COMPLETION FOR THE LAKEVIEW ELEMENTARY SCHOOL - RENOVATION PHASE 2: PARTS THREE AND FOUR PROJECT Description This is the Part Three and Four of Phase 2 of the project to achieve completion. The architect has prepared the Certificate of Substantial Completion and the final punch list. These phases are the last two phases of the contract and are substantially complete in accordance with the contract documents. A copy of the final punch list is available for review at the Construction Services Department. Recommendation That the work performed by P.J. Hayes, Inc, dba Tandem Construction for the Lakeview Elementary School - Renovation Phase 2: Parts Three and Four be accepted as substantially complete as of 8/14/2008. Contact LEMPE & COLLINS Financial Impact N/A Attachment: BAIenc9-16-08LkvwHVAC-Ph2Part3&4SC.pdf |